RE: Planned Standard Costs for Assembly Items

Hi There. 

I have an assembly item, whose standard cost needs to be updated. 

I have run the ‘Planned Standard Cost Roll Up’ after selecting the assembly item.

My understanding is that this should;ve generated a planned standard cost for the standard cost version. 

The roll up ran without errors though did not generate any planned standard cost records.

Am I missing a step?

Lefemmenikita Rookie Asked on October 15, 2023 in Manufacturing.
Add Comment
2 Answers

Thanks Anil2204. This is an item that has previously used standard cost successfully.

The item was made inactive and then made active again recently.

The standard cost version was selected on the standard cost roll up screen

Rookie Answered on October 16, 2023.