Set fixed quantities for a component in a bill of materials
Hi,
Is there any way to set up a fixed quantity for a component in a Bill of material? I mean setting a fixed component quantity that is independent of the quantity being manufactured. for example to paint 100 meters I use a roller, just like when I paint 200 meters.
Do you know how can we do this?
Many thanks in advance!!
Angel
The roller is not a component of the bill of the materials in that scenario, it’s more of a resource that needs to be planned around. I assume advanced manufacturing would have the capabilities to handle this.
Hi,
This is a usual functionality in other ERPs I know, and is always a functionality of the bill of materials (JDEdwards, Oracle EBS, Oracle ERP cloud).
Do you know how to ask for a knew functionality for NetSuite?
Many thanks for your answer!!
Angel
Greg
Hi Angel,
Have you found a way to address your issue?
If so, how did you?
I have the exact same requirement and I don’t believe there an out of the box feature to support this.
Greg